Kitchen renovation cost in Pakistan: what to spend on
Kitchen renovation cost in a 5 or 10 marla house in Pakistan can run anywhere from a modest few hundred thousand rupees to well over a million, and the gap usually comes from three decisions: what the cabinets are made of, how much of the old kitchen you keep, and whether you change the plumbing and gas layout. Get those three right and the rest is just tidy execution.
All figures below are planning ranges as of late 2026. Material and labour rates in Lahore, Karachi, Islamabad and Peshawar differ and shift month to month, so use them to compare quotes, not to replace one.
Decide the scope before you call anyone
Contractors price what you describe. If you say "renovate the kitchen", you will get five quotes that cannot be compared. Write down which of these you want:
- Cosmetic refresh (paint, new counter, new hardware, maybe tiles over the existing ones): roughly PKR 150,000 to 400,000.
- Mid-level renovation (new cabinets, new counter, backsplash tiles, new sink and tap, light and exhaust upgrade): roughly PKR 500,000 to 1,200,000.
- Full rebuild (changing the layout, moving gas or water lines, new floor, and a modular kitchen): from about PKR 1,200,000, often considerably more with imported hardware.
A typical 10 by 12 foot kitchen in a 5 marla house sits in the middle band. If you are tempted to move the sink to the other wall, price that separately, because new drain lines often cost more than the cabinets they serve.
Sequence matters more than brand
The most expensive mistakes I see come from doing things in the wrong order. A kitchen should go like this:
- Demolition and clearing, including removal of old tiles if you are re-tiling.
- Plumbing, drainage and gas line changes, with a pressure test before anything is closed.
- Electrical points: socket positions for the oven, fridge, microwave, water dispenser and chimney, plus a dedicated point for any heavy appliance.
- Wall and floor tiling, then grouting.
- Countertop measurement, which should be taken after the cabinets are fixed, not before.
- Paint and final fittings.
Our checklist on plumbing and electrical checks before plaster is written for new builds, but the same logic applies once you open a kitchen wall.
Cabinets: where the money goes
Cabinets are usually 40 to 55 percent of a mid-level budget. Prices are quoted per running foot, and they vary widely with the material and the hardware.
- Marine plywood or good MDF with a laminate or wrap finish is the common middle option. It handles humidity better than cheap particle board, but check the edge sealing, because that is where water enters.
- Solid wood looks beautiful and costs more; it needs proper finishing and can swell in a damp kitchen.
- Aluminium and PVC systems do not rot and suit coastal Karachi, where humidity and salt air attack plywood faster.
Ask each carpenter: what is the core board, what is the edge banding, which hinges and drawer channels will you fit, and what is the warranty? Soft-close hardware from a reputable maker adds noticeable cost, yet it is the part you touch every day, so pay for hinges before you pay for fancy doors.
Counters, tiles and splashbacks
For the countertop, granite is common and durable; quartz costs more and resists staining better. Marble looks lovely but stains from lemon, tea and oil. Measure the counter yourself, get a rate per running foot, and confirm what is included: cutting for the sink and hob, polishing of edges, and fixing.
For walls and floor, a good anti-skid tile on the floor matters more than anything on the wall. Splashbacks behind the stove can be tile or toughened glass. Whatever you choose, keep a few spare tiles from the same batch, since colour varies between lots.
Ventilation and gas safety
Pakistani cooking is oil and steam heavy. A proper exhaust or chimney that vents outside, not into a ceiling void, protects the paint, the cabinets and your lungs. Use rigid or smooth ducting with the shortest run.
If your kitchen has piped gas, have a licensed fitter handle any changes, use certified flexible hoses, and test for leaks with soapy water, never a flame. Keep the gas meter accessible. In winter, when many homes run heaters and geysers, ventilation matters even more.
Get quotes you can compare
Ask three contractors to quote the same written scope and the same drawing. Insist on a line-by-line list with units and rates; our guide to comparing contractor quotes with a BOQ shows how to do that. Then use the construction cost calculator to sanity-check totals, and see our note on labour-only contracts before you decide whether to buy materials yourself.
Payment terms matter too. A reasonable structure is a modest advance for materials, then staged payments tied to finished work such as plumbing complete, tiling complete, cabinets fixed. Never pay the final portion until the tap runs, the drain clears, the hob lights and every drawer closes.
Watch the hidden costs
Budgets slip in predictable places:
- Old pipes behind the wall that turn out corroded
- Uneven floors needing a levelling screed before new tiles
- Debris removal, which can be a separate charge
- Electrical rewiring when the old circuit cannot take new appliances
- Waiting time if the carpenter and tiler overlap
Set aside a contingency of 10 to 15 percent of the total. Spend it only on real surprises, not on upgrades you thought of halfway through.
Lighting and storage details that get skipped
Add under-cabinet LED strips at the design stage, because chasing wires after tiling means breaking tiles. Plan a tall pantry unit or pull-out for oil bottles, flour and spices, and leave a 450 mm gap beside the fridge for ventilation. Put the bin inside a cabinet, not under the sink where leaks hide. These small decisions cost little on paper and save the most frustration later.
Should you renovate now or wait?
Winter is a decent time to renovate indoors because tile adhesive and paint behave well in mild weather, though very cold nights in the north slow curing, and smog days in Punjab can make dust control harder. Prices of cement, tiles and steel move from month to month, so check current rates when you finalise the quote rather than relying on what a neighbour paid last year.
If you plan to sell or rent the house within two or three years, spend on the things that buyers and tenants notice: clean surfaces, working ventilation, solid cabinets and a counter that does not stain. Skip the imported fittings. A home valuation estimate can give you a feel for whether a given upgrade will matter at all.
Your next three steps
This week, measure the kitchen, draw a rough sketch, and write the scope in plain sentences. Next week, get three itemised quotes and visit one completed kitchen by each contractor. Then pick based on detail and references, not on the lowest total. Book the work so that gas, water and wiring are finished first, and keep a daily photo log. A kitchen is the one room you will use three times a day for the next decade, so it deserves a slow start and a fast finish.
Frequently asked questions
How much does a kitchen renovation cost in Pakistan?
As a late 2026 planning range, a cosmetic refresh costs roughly PKR 150,000 to 400,000, a mid-level renovation with new cabinets and counters PKR 500,000 to 1,200,000, and a full rebuild from about PKR 1,200,000. City, materials and layout changes move these numbers considerably, so get itemised quotes.
What is the right order of work in a kitchen renovation?
Do demolition first, then plumbing, drainage and gas changes with a pressure test, then electrical points, tiling, countertop measurement after cabinets are fixed, and finally paint and fittings. Doing wiring or plumbing after tiling means breaking finished work and adds cost.
How much contingency should I keep for a kitchen renovation?
Keep roughly 10 to 15 percent of the total budget aside. Hidden problems such as corroded pipes, uneven floors, debris removal and old wiring are common in Pakistani homes. Spend the contingency only on real surprises, not on upgrades decided midway.
Keep reading
Contractor payments in Pakistan: a 5 marla stage plan
Contractor asking for 40% upfront? Here is a milestone schedule for a 5 marla build, with retention and the clauses that keep your leverage.
8 Nov 2026 6 min read
uPVC vs aluminium windows in Pakistan: what to pay
Window quotes look wildly different because frames, glass, seals and hardware are bundled together. Here is how to compare them for a 10 marla house.
7 Nov 2026 6 min read
Cold weather concreting in Pakistan: protect a winter pour
Frost in the first two days can quietly weaken a roof slab. Learn when to delay, how to cover and cure, and when shuttering can come off.
17 Nov 2026 6 min read