Plumbing and electrical checks before plaster in Pakistan
A mason will often tell you that plaster is where the house gets finished. I tell homeowners it is where the house gets hidden. Once plaster goes over the walls, every pipe, conduit and junction box behind it is out of sight for the next thirty years. Fixing a leaking pipe or a badly placed socket after plastering means breaking finished walls, and the repair bill is multiples of what checking it cost.
This guide covers the rough-in stage for a typical 5- to 10-marla house in Pakistan: what to inspect, what to test and what to photograph before the plasterers arrive. It applies in Lahore, Islamabad, Karachi, Peshawar and smaller towns alike, though local practice and material availability differ.
What rough-in means and why it matters
After the grey structure (columns, slabs and brick or block walls) is up, three trades work inside the walls before plaster: plumbing, electrical and, where relevant, gas and AC pipework. Their work gets chased into the masonry or fixed in slabs and then covered.
The danger is that each trade is paid separately, works on a different day and often finishes before anyone checks them together. I have seen a bathroom wall chased for a hot-water pipe where the electrician had already buried a conduit, so the pipe was bent around it and later cracked. I have seen the AC drain pipe slope the wrong way. Nobody lied; nobody checked.
Step one: freeze the layout on paper
Before any chasing starts, mark the position of every fixture on the wall with chalk or a marker, then photograph it. That means:
- Every socket, switch, fan point, light point and TV or internet outlet
- Every tap, geyser connection, WC, basin and shower mixer
- AC split positions, indoor and outdoor units, and the drain route
- The kitchen: gas cooker point, hood, hob and sink
Decide kitchen layout first, because the kitchen has the most connections. If you will install a modular kitchen or a built-in oven later, confirm the cabinet maker's measurements before the sockets are fixed. Sockets behind a cabinet are a common and silly mistake.
Our construction cost calculator can help you budget the overall build, but individual line items such as fittings vary by brand and city.
Plumbing: what to check
Pipe material and joints. Most new houses now use PPR pipes for hot and cold water, with fusion-welded joints. Check that the pipes are the ones named in the contract, not a thinner substitute. Look for clean, even weld beads, not blobs or gaps. For drains, use heavy-grade uPVC with proper solvent joints.
Hot and cold separation. Keep hot and cold lines apart, and insulate hot lines. Winter is when this matters, since uninsulated hot lines lose heat and bathrooms wait longer for hot water.
Slope on drains. Waste pipes need a continuous fall. If the plumber cannot show it with a spirit level, he has guessed. Ask for the level to be applied while you watch.
Pressure test before covering. This is the single most valuable test. Plug the open ends, pressurise the system with a hand pump or a test pump to a pressure agreed with the plumber (often around 1.5 times the working pressure; ask your plumber or engineer for the right figure for your pipe class) and leave the system for several hours, ideally overnight. If the gauge drops, there is a leak. Repeat after any repair. Take a photo of the gauge at the start and end.
Concealed fittings. Check that valves, isolating stops and the geyser feed have accessible shut-offs. A hidden valve without an access panel is a trap.
Electrical: what to check
Conduit and cable sizing. Cables should be of the gauge specified in your plan, from a known manufacturer, and run inside conduit. For lighting circuits, power sockets, ACs and the kitchen, use separate circuits. Heavy loads such as AC units and geysers should have their own cable and breaker. If your electrician proposes to "tap" an AC off a general socket circuit, say no.
Earthing. Ask where the earth rod is and how it is connected. A proper earth is cheap at the construction stage and nearly impossible to add later. Every socket needs an earth connection.
Junction boxes. Every joint should sit in an accessible box, not buried in plaster. Make sure each box has a note in your photo log so you know where it is.
Phase balance and the distribution board. For larger houses, ask the electrician to explain how loads are shared across phases. Have the board labelled clearly.
Solar readiness. If you may add solar panels in future, ask the electrician to leave a spare conduit from the roof to the distribution board. It costs little now and saves chasing a finished wall later. Many Pakistani households are adding solar because of the grid tariff, and a spare conduit keeps that option open.
Insulation resistance test. A basic test with a megger on the circuits before they are covered can reveal a nicked cable. Ask whether your electrician has the tool; if not, a hired technician can do it for a modest fee.
Gas, AC and low-voltage
Gas piping needs the correct pipe and fitting type and must be pressure-tested. In many areas, gas connections are restricted or slow, so confirm with the utility before you assume gas will be there. If it is not available, plan electric or LPG alternatives and note the pipework you will need.
For AC, run refrigerant pipes in insulated copper, fix the drain pipe with a clear fall and put outdoor unit brackets where the unit can be serviced safely. Add conduits for internet, CCTV and intercom while the walls are open.
Your photo and drawing log
Take clear photos of every wall before plaster: wide shot and close-ups, with a tape measure in frame so distances show. Mark them by room and wall. Store them in a shared folder and also on paper. When you want to hang a heavy cabinet or drill for a curtain rail in 2035, you will know what is behind it.
Ask each contractor to sign off the work: "plumbing tested on date X, passed." It is a small ritual that stops arguments later.
Pay for finished work, not promises
Contractors usually want payment stage-wise. Tie the plumbing and electrical stage payments to the tests above, not to the date. Keep a retention, a small slice of the contract value released only after the system has run for some weeks without problems. How much retention is reasonable depends on your contract and the trade, so agree it before work starts.
If you are building on a plot you bought through the plot finder, or hiring someone through Sakunat's agent directory, ask for references on previous house work and visit one finished house if you can.
A checklist you can print
- Layout marked and photographed for every room.
- Kitchen and bathroom fixtures confirmed against cabinet and sanitary ware dimensions.
- Pipe type, size and brand match the contract.
- Water system pressure-tested and logged with photos.
- Drain slopes checked with a level.
- Electrical circuits separated for AC, geyser and kitchen.
- Earthing verified.
- Spare conduits for solar, internet and CCTV.
- Photo log shared and backed up.
- Stage payment released only after sign-off.
Before plaster day
Plan a full day for this inspection, one or two days before the plasterers are due, so you can fix problems without losing the schedule. If you are not on site, hire an engineer for a half-day visit. It costs a fraction of one repaired wall. Plaster looks like progress, but progress that hides a mistake is just a more expensive way to find it.
Frequently asked questions
Why pressure-test pipes before plastering?
Once plaster covers the wall, a leak means breaking finished surfaces. A pressure test holds the system under pressure for several hours, ideally overnight, so a gauge drop reveals leaks while pipes are still visible. Agree the test pressure with your plumber or engineer and photograph the start and end readings.
Do AC and geyser need separate electrical circuits?
Yes, heavy loads should have their own cable and breaker rather than tapping a general socket circuit. Sharing risks overheating and trips. Specify separate circuits in the electrical plan before chasing starts, and ask your electrician to confirm cable gauge and earthing for each one.
What should I photograph before plaster?
Take wide and close-up photos of every wall showing pipes, conduits, junction boxes and valves, with a tape measure in frame. Label by room and wall and back them up. Years later you will know where it is safe to drill and where fittings sit.
Keep reading
Electrical wiring plan for a 10 marla house in Pakistan
Decide loads, circuits and point locations on paper before plastering. A few spare conduits and a circuit schedule save expensive wall repairs.
18 Nov 2026 6 min read
Underground water tank size and placement for a Pakistani house
Size the underground tank, place the pump, pick pipes and test them before plaster hides the walls. A site-level plumbing guide.
21 Nov 2026 7 min read
Underground water tank size Pakistan: a 10 marla plan
Count people, not marlas. A simple litres-per-day method, a worked 10 marla example, and the checks to demand before the slab is cast.
27 Oct 2026 6 min read