Underground water tank size Pakistan: a 10 marla plan
Most people drawing up a house plan in Lahore, Faisalabad or Islamabad spend weeks on the kitchen layout and ten minutes on the underground water tank. Then the first summer arrives, the supply timings shift, the motor runs dry at 6 a.m. and a family of seven discovers that the tank was sized by the mason's guess. Getting the underground water tank size Pakistan homes need right costs nothing at the design stage and a great deal after the slab is cast.
I'll give you the method I'd use on site, with an example for a 10 marla house. Treat the figures as planning numbers, not code requirements: local supply patterns, municipal rules and your engineer's advice come first.
Start with the household, not the plot
A plot size tells you almost nothing about water demand. A 5 marla house with three generations living in it can use more than a 1 kanal house with a couple and one child. So count people, not marlas, and include the people who are not there all the time: the live-in help, the guests who stay for weeks, the relatives who arrive for Eid.
For rough planning, many designers use somewhere between 100 and 150 litres per person per day for household use, higher if you have a garden, a car you wash at home, or a bathroom set that uses a lot per flush. Treat that range as a starting estimate and adjust for your own habits.
Work out how long supply can fail
The second input is the longest stretch your area goes without water. In some parts of Karachi, supply can be a few days apart or arrive by tanker. In other areas with a tubewell, the limit is power cuts rather than water. Ask the neighbours on both sides, not the developer. Then plan for two days of storage as a minimum, and three if your street is known for unreliable supply.
A worked example: 10 marla, family of 8
A 10 marla plot is about 2,722 sq ft of land. Say eight people live there, including help, at 150 litres each per day. That is 1,200 litres a day. Two days of storage is 2,400 litres. Add a safety margin of about 25% and you land near 3,000 litres.
Convert it for the mason. One cubic foot is roughly 28.3 litres, so 3,000 litres is about 106 cubic feet. A tank inside dimensions of 6 ft long by 5 ft wide and 3.5 ft of water depth gives 105 cubic feet. Add some height above the water line for air and the inlet pipe, so the excavated depth is about 4.5 ft to 5 ft.
If you also want to water a lawn or wash vehicles on site, add that demand separately instead of hoping the margin will cover it.
Underground tank and overhead tank are a pair
An underground tank is the reservoir. The overhead tank on the roof is your pressure source. A common rule of thumb is to size the overhead tank to hold roughly a day's use, which here is about 1,200 to 1,500 litres, often delivered by two or three plastic tanks. If the overhead tank is too small, the motor starts and stops all day. If it is too big, the roof carries more weight than the slab design assumed, so tell your structural engineer the final tank weights before the slab is poured. A full 1,500 litres weighs about 1.5 tonnes before you add the tank itself.
Pumps and pipework
The tank is only half the system. A small booster or transfer pump lifts water from the underground tank to the roof, and its capacity should match the overhead tank so it fills in about 20 to 30 minutes rather than running for hours. Fit a non-return valve on the suction side and a float switch in the overhead tank, so a forgotten motor does not overflow onto the roof at night. Use proper-grade pipe and fittings, not the cheapest bundle in the market, and keep a spare motor capacitor in the house.
Where the tank goes on the plot
Do not place it casually under the car porch or beside a boundary wall.
- Distance from the septic tank and soakage pit. Keep a clear gap. Your engineer will specify it, and it depends on soil type and the water table. Cross-contamination is the most serious risk in the whole job.
- Distance from foundations. A tank excavated too close to a footing can undermine it. Your structural drawings should show the tank's location, not leave it to be decided on the day.
- Access. You need a manhole cover you can open, so no heavy vehicle should park over it unless the cover and slab are designed for that load.
- Slope. Keep the inlet higher than the outlet, and make sure the floor slopes to a small sump for cleaning.
What the contractor should build
This is where I have seen corners cut. A good tank has a base slab, walls in reinforced concrete or well-built brick with plaster, and a cover slab with a manhole. Ask for three things in writing:
- Waterproofing inside. Use a waterproofing additive in the mortar or a coating suitable for potable water, applied in the manufacturer's coats and given its curing time. Plain cement plaster alone can seep.
- Rounded inner corners. Sharp corners trap sediment and are hard to scrub.
- A fill test before you backfill. Fill the tank and leave it for 48 to 72 hours with the level marked on the wall. If the level drops beyond evaporation, find the leak now, while the walls are still exposed.
Costs vary widely by city, soil, material prices and finish. Use the Sakunat construction cost calculator for the whole house and ask your contractor for the tank as a separate line, so it is not lost in the lump sum.
Cleaning, covers and the details people forget
Add a small sump, a washout pipe, a vent with a mesh against insects and a lid that fits tightly. Plan to clean the tank at least once a year, and more often if the water is hard or comes from a tanker. If you ever need to extend the tank, deciding on a cut-in point now is cheaper than breaking walls later.
If your plot is in a low-lying area, check the water table and flood history before you dig deep. A tank in high groundwater can float when empty, which is a real engineering problem and not a rumour. Your engineer should check this and, if needed, design for it.
Before you finalise the plan
Gather the numbers: household size, longest supply gap, your plot's dimensions and the location of the septic system. Then ask your engineer or architect to mark the tank on the drawings, with sizes and levels, before the contractor starts. If you are still choosing a site or a built house, our plot finder and the unit converter for marla and kanal help you size things properly. Municipal rules and material prices change, so confirm the current requirements with your engineer and the local authority. Good tank planning costs a few hours now and saves a summer of problems later.
Frequently asked questions
What size underground water tank does a 10 marla house need?
It depends on people and supply gaps, not plot size. For eight people at about 150 litres each daily, two days of storage plus a 25% margin gives roughly 3,000 litres, or about 106 cubic feet. Confirm your own numbers with your engineer, including garden or vehicle use.
How much water does one person use per day in a Pakistani home?
Many designers plan between 100 and 150 litres per person per day for household use as a rough starting point. Gardens, vehicle washing, large families, guests and high-flow fittings push it higher. Treat it as an estimate and measure your own usage if you can.
How do I check my new water tank for leaks?
Before backfilling, fill the tank, mark the water level on the wall and leave it for 48 to 72 hours. If the level falls more than evaporation would explain, there is a leak. Repair it while the walls are exposed, then retest before you cover and connect the tank.
Keep reading
Underground water tank size and placement for a Pakistani house
Size the underground tank, place the pump, pick pipes and test them before plaster hides the walls. A site-level plumbing guide.
21 Nov 2026 7 min read
Solar system for a 10 marla house: size it, plan the roof
Before you accept an installer's 'one size' quote, learn to size panels from your bills, map your roof and compare grid-tied and hybrid setups.
2 Nov 2026 6 min read
How to compare contractor quotes in Pakistan with a BOQ
Lump-sum quotes hide shortfalls. Learn which BOQ lines to compare, where contractors cut corners, and what to fix in the contract.
30 Oct 2026 6 min read