Electrical wiring plan for a 10 marla house in Pakistan

By Sakunat18 November 2026 6 min readAI-assisted
Electrician fitting conduit and wiring boxes in an unplastered brick wall of a new house in Pakistan

Plaster is on, the paint is booked for Monday, and your electrician asks: "Sir, where do you want the AC point in the bedroom?" If you are standing in a finished room, the answer costs you a chiselled wall and a repaint. If you answer before plastering, it costs a few metres of conduit. That gap is why a written wiring plan is worth more than any single material choice.

A wiring plan is a few pages: loads, circuits, point positions and a spare-conduit route.

This guide is for a 10 marla (about 2,700 sq ft plot) double-storey house, but the logic scales down to 5 marla or up to a kanal.

Plan the loads before the points

Start with what you will plug in, not with sockets. A typical 10 marla family house in Lahore, Islamabad or Faisalabad will eventually run:

  • 4 to 6 split ACs (1.5 ton units, often inverter type).
  • Geysers or a gas-electric combination, and possibly an instant water heater in the kitchen.
  • A water pump with an underground tank.
  • An oven, microwave, fridge, deep freezer and washing machine.
  • A solar system, now or later.

Add up the heavy items and ask an engineer or a qualified electrician to size the main supply and distribution boards. Do not size by guess or by what the neighbour did. Check your sanctioned load with your distribution company too, because the connection you apply for decides the meter and service cable you need.

Circuits, not just wires

For-sale sign in front of a modern house
For-sale sign in front of a modern house

The common mistake is running one thick wire from the board to a loop of rooms. The better pattern is separate circuits:

  • Lighting circuits, one per floor or zone, so a fault does not black out the whole house.
  • Socket circuits, separate from lights, again per floor.
  • Dedicated lines for every AC, each on its own breaker.
  • Dedicated lines for the kitchen heavy appliances, geyser and pump.

This is how a house tolerates a tripped breaker in one room without losing the fridge. Ask for a circuit schedule, a simple list of which breaker feeds which points, and insist it is handed over with the keys. You will need it the day something trips at night.

Wire gauge and brand

Cable sizing is a safety issue, not an upgrade. As a general site practice, many builders use thinner cable for lights and thicker for sockets and ACs, and heavier again for the main feed. Exact sizes depend on the load and run length, so take them from the electrician's design rather than from a rule I quote here. What you can control:

  • Buy cable from an authorised dealer and keep the invoice; counterfeit and under-gauge cable exists in the market.
  • Check the cable is copper, with markings for size and manufacturer along the length.
  • Ask that the earth wire runs to every socket, and that the house has a proper earthing pit. I have seen new houses with earth terminals on the sockets and nothing connected behind them.
  • Use PVC conduit buried in the wall, never loose wire chased into plaster.

Pay a little more for good cable and breakers. Wiring sits behind finished walls for thirty years.

Where points should go

Walk each room with furniture sketched on a floor plan. For a 10 marla house, sensible ideas include:

  • Master bedroom: switches at both door and bedside, two sockets on either side of the bed, a TV point, an AC point high on the wall with a drain route planned, and a socket near the dressing area.
  • Kitchen: more sockets than you think, at counter height, for kettle, blender, air fryer and toaster, plus separate points for the fridge, microwave and oven.
  • Lounge: TV, router and set-top points placed together, with conduit for network cable from the router location.
  • Outside: a weatherproof socket in the porch, lighting for the gate and boundary wall, and a point for a car charger or a future solar inverter.
  • Roof: a socket and a light for the water tank and solar panels, with conduit between the roof and the main board.

Add spare conduit. A few empty pipes between floors and from roof to board cost little now and save wall cutting later when you add solar, cameras or a UPS.

Solar and backup: plan the route now

If you may add solar within a few years, decide where the inverter, battery and board will live, and run an empty conduit from the roof to that spot. Sizing the system is a separate exercise; the wiring point is that the AC-side connection and the earthing for panels should be known before plaster, not after. Keep the inverter away from direct sun and from the kitchen's grease and steam.

What it costs

Rates move with copper and labour, and they differ between Karachi, Lahore, Peshawar and smaller cities, so treat any range as a starting point for quotes. Wiring is usually quoted per point (light, fan, socket) for labour, with material bought separately, or as a lump sum for labour and material together. Get at least three quotes, ask each to list cable size, breaker brands, number of points and the number of circuits, and compare line by line.

For a rough check of where electrical work sits in your whole budget, use the construction cost calculator. Electrical typically takes a modest share of the grey structure and finishing total, but a thin spec saved today becomes a rewire bill tomorrow.

Lighting and switches: small choices that you live with

Decide the lighting style before the ceiling work, because false ceilings and cove lights need their own supply points. Two-way switching on staircases and long corridors is cheap to run now and impossible to add neatly later. In bedrooms, put one switch by the door and one by the bed for the main light, so nobody crosses a dark room. For the kitchen, separate the work-surface lights from the main light. LED fittings run cool and draw little, which also lets you use thinner lighting circuits without worry, though the cable should still follow the electrician's design.

Fan points matter in Punjab and Sindh summers, when load shedding or a failed inverter means the ceiling fan is your only cooling. Keep a fan point in every bedroom even if you install ACs, and run it from a circuit that can later be switched to backup power.

Mistakes I see on site

  • Chasing walls after plaster to add points that were left out.
  • One breaker for several ACs. It trips in June, usually at 3 pm.
  • Joints inside walls. Every joint should sit in an accessible box, not buried.
  • No labelling on the distribution board.
  • Cheap switches and sockets in high-use spots, which loosen and spark within a couple of years.
  • No earth, or earth connected to the water pipe.

Inspect before you close the walls

Wiring should be tested before plaster covers it. Before it does:

  1. Photograph every wall with conduit visible, with a tape measure showing distance from the floor and the corner. These photos will tell you where it is safe to drill later.
  2. Check conduits are continuous and not crushed.
  3. Ask the electrician to do a continuity and insulation test, and note the date.
  4. Confirm point count against your marked-up plan.
  5. Keep the plan, the circuit schedule and the photos in one folder.

If you are still choosing a contractor, make every bidder price the same written scope from the property tools hub estimate you started with. Before the plaster crew arrives, do the walk-through above with the electrician and mark each point in chalk. Ten minutes in each room beats a month of repair.

#wiring#construction#10 marla#electrical#solar

Frequently asked questions

When should I finalise electrical points in a new house?

Before plastering starts. Walk each room with the furniture layout, mark every switch, socket and AC point in chalk, and get the electrician to confirm the count against a written plan. Adding points afterwards means chiselling finished walls and repainting, which costs far more than adding them early.

How many circuits does a 10 marla house need?

There is no fixed number, because it depends on your appliances. A sound pattern is separate lighting and socket circuits per floor, a dedicated breaker for every AC, and dedicated lines for the geyser, kitchen appliances and water pump. Have an electrician size the supply and boards for your actual loads.

Should I leave spare conduit for solar?

Yes. Running an empty conduit from the roof to the planned inverter location costs little during construction. It also helps for cameras, network cable and a UPS later. Photograph the conduit routes before plaster so you know where it is safe to drill afterwards.