A tile shop in Lahore's Ravi Road or Karachi's Shershah will quote you a rate per square foot, and that single number is what most house owners compare. Then the delivery arrives and the bill is 15 percent higher than the arithmetic you did on the back of an envelope. Tile wastage is the first culprit, and tiles are one of the few finishing items where the sticker price and the real price drift far apart, and it is worth an hour of planning before you hand over an advance.

This guide walks through how to size, grade and order floor and wall tiles for a typical 5 to 10 marla house, with the hidden costs spelled out.

Start with the area, not the rate

A 10 marla house is roughly 2,722 square feet of plot (a marla is taken as 272.25 sq ft), but your tile area is a different number. Measure the covered floor area room by room, then add the bathrooms' walls and the kitchen splashback separately. You can use the marla and kanal unit converter if your plan is in marla and the shop speaks in square feet.

As a planning shortcut, many builders tile 70 to 85 percent of the covered area with floor tiles, because lounges, bedrooms, corridors and kitchens get tile while porches, terraces and some bedrooms may get marble, wood-look planks or cement finish. Wall tiles in bathrooms typically run to full height or to roughly 7 feet, and kitchens often get a splashback of 2 to 4 feet above the counter.

Write the area down for each space. That list becomes your order sheet, and it will stop the "just send a few extra boxes" habit that quietly inflates the bill.

Wastage: add the right amount, not a guess

Bricklayer building a wall on a housing site
Bricklayer building a wall on a housing site

Tiles break, get cut at the edges and arrive with the odd chipped corner. Adding wastage is correct. Adding too much is a common way to overspend.

  • Straight lay, 2 ft by 2 ft tiles in a regular room: allow roughly 5 to 8 percent.
  • Diagonal lay or lots of small rooms and corridors: roughly 10 to 15 percent, since more tiles are cut at angles.
  • Large format tiles (2 by 4 ft, or bigger): plan on 8 to 12 percent and a careful layout, since one breakage costs a lot more.
  • Bathrooms with niches, windows and corners: allow 10 to 12 percent.

Ask the mason to sketch the layout before the final order. For an irregular room, mark where the cuts land. The offcuts of one room often serve another, and a good mason will use them.

Keep at least one extra box after the job. Tile lots (the "batch" or "shade" number printed on the carton) differ from one production run to the next, and a box ordered six months later from a different lot can be visibly darker or a few millimetres off in size. This matters for any future repair.

Grade, shade and size: the three things on the carton

Open a carton on the shop floor and read the label. You are looking for three details.

Grade. Tiles are typically sorted into grades, with the top grade having the fewest visual and dimensional defects. Local and imported brands use different naming, so ask the dealer to explain what their grade means, and insist that the invoice carries the grade you were promised. A lower grade can be a perfectly sound choice for a store room, and an expensive mistake in a lounge.

Shade or batch number. All boxes for one room should share the same number. Check this on delivery, before the tiles are laid, not after.

Calibre (the actual size). Two tiles with the same nominal size can differ by a millimetre or two. A larger variation makes grout lines uneven, and the mason ends up compensating with thicker joints. Open a few boxes and stack tiles face to face to check.

Tile type by room

Different rooms ask different things of a tile.

  • Lounge, bedrooms and corridors: polished porcelain or glazed porcelain in a larger format looks clean and cleans easily. It can be slippery when wet, which matters if you have elderly relatives or small children.
  • Kitchen: a matt or lightly textured porcelain floor, and a glazed ceramic or porcelain splashback that wipes clean. Avoid deep grout lines behind the stove.
  • Bathrooms: a slip-resistant floor tile with a visible texture. Walls can be glossy, but the floor should not be. Ask for the tile's slip rating if the dealer has it.
  • Porch, driveway and terrace: weather-resistant tiles or paving. Normal indoor tiles can crack under sun and cold.
  • Stairs: tiles with a nosing or an anti-slip edge. This is where cheap tiles cause genuine injuries.

If you are comparing materials, our notes on how to compare contractor quotes with a BOQ show how to ask a contractor to price tile supply and fixing separately, which makes comparison honest.

The costs nobody puts on the first quote

The tile is only part of the job. Here is what typically appears afterwards.

  1. Labour per square foot. Fixing rates vary by city, tile size and the mason's reputation, and large-format tiles cost more to lay. Get a rate per square foot, state clearly whether it includes surface preparation, and agree whether the mason or you supply the supporting materials.
  2. Adhesive or cement bed. Many Pakistani jobs still use a cement and sand bed. Tile adhesive costs more and is faster for wall tiles and large floor tiles, where a thin, even bed matters. Ask the mason which they plan to use and why.
  3. Grout and spacers. The grout colour changes the look of the whole floor. Ask to see a sample board before it goes into the joints.
  4. Levelling. If the sub-floor is uneven, the floor needs a screed first. Tiling over an uneven base produces hollow-sounding tiles that crack later.
  5. Cutting and polishing at edges, door thresholds and niches, which often come as a separate line.
  6. Transport and unloading. Heavy cartons on upper floors are an actual cost, and a reason to settle where they will be stored.

Add them up before you decide a cheaper tile is a bargain. A tile that saves PKR 30 per square foot but needs an extra day of levelling per room may not save anything.

Receive, inspect, then pay the balance

When the delivery arrives, do the checks while the truck is still outside, if you can.

  • Count the cartons against the invoice.
  • Check that every box carries the same shade and batch number.
  • Open and inspect at least one box in ten for chips and size differences.
  • Take photographs of damaged boxes and ask the driver to note them on the delivery slip.
  • Store the boxes flat or on their edge as the manufacturer says, away from rain and out of the way of the mixer.

Pay the balance only when the quantity and grade are confirmed. If a dealer refuses returns on unopened cartons, ask for that in writing, since a return policy matters when you have over-ordered. Reasonable dealers will usually take back full, unopened cartons of a current line, perhaps with a handling deduction. Agree that before you order.

Laying: what to watch on site

I have stood in enough half-finished houses to know where tile jobs go wrong, and it is almost never the tile.

  • Hollow spots. Tap tiles with a wooden handle after they set. A hollow sound means the bed is not full. It is far cheaper to lift one tile today than a whole floor next year.
  • Lippage. Run your hand over the surface. Edges that catch your palm are uneven, and in a lounge they also catch light and show.
  • Slope in wet areas. Bathroom floors need a fall toward the drain. Pour a bucket of water on the floor and watch where it goes.
  • Expansion joints along walls and in large floors, so the floor can move slightly without cracking.
  • Curing. Do not walk on a fresh floor or move furniture for the period the mason advises.

Before you place the order

You can keep tile spend sensible with a small routine. Write the area per room and add the wastage figure. Get at least two quotes for the same grade and size, supply and fixing priced separately. Ask for the shade number on the invoice. Order the extra box. And use the construction cost calculator to see how finishing items like tile sit within your total build budget, so a lounge floor does not quietly eat the money for bathrooms or electricals.

Material rates move month to month, so confirm current prices with two or three dealers on the day you order. If you are still choosing a site or society, you can browse plots and homes for sale before committing to a build. Tile is a once-in-fifteen-years decision for most families. An hour spent measuring today saves a lot of arguing later.

#tiles#finishing#construction#budget#house build

Frequently asked questions

How much extra tile should I order in Pakistan?

For a straight lay in regular rooms, allow about 5 to 8 percent wastage. Diagonal layouts, small rooms and bathrooms need roughly 10 to 15 percent, and large-format tiles about 8 to 12 percent. Keep one unopened spare box afterwards, because later batches can differ in shade and size.

What do grade and shade number mean on a tile carton?

Grade ranks the tile by visual and size defects, with the top grade having the fewest. The shade or batch number identifies the production run. Boxes for one room should share the same shade number, otherwise colours and sizes can visibly differ once laid.

Why does the final tile bill exceed the shop quote?

The shop rate covers only the tile. Fixing labour, adhesive or cement bed, grout, levelling the sub-floor, edge cutting, transport and unloading are usually extra. Ask for supply and fixing priced separately, and add wastage, before comparing quotes from two or three dealers.