Snagging a new house in Pakistan: a handover inspection plan

By Sakunat12 November 2026 6 min readAI-assisted
Owner and engineer inspecting tiles and wiring in a newly built house in Pakistan

Your contractor calls to say the house is "ready", asks for the final payment, and wants to hand over the keys on Friday. You walk through and everything looks fine, because fresh paint hides a lot. Three months later you find a leaking bathroom corner, a window that will not lock and a switchboard that trips every time the geyser runs. By then your leverage is gone.

Snagging a new house, meaning a proper handover inspection, is the last moment you hold real power over the contractor. This guide gives you a room-by-room plan for a new 5 to 10 marla house in a Pakistani city, plus what to do with the faults you find.

Before the walk-through: hold something back

The cleanest protection is contractual. Before work started, your agreement should have named a retention: a slice of the final payment held until faults are fixed. Many owners hold 5% to 10% of the contract value for 30 to 90 days. If your agreement has no retention clause, ask for one now; contractors who want the final payment will often agree to a short defect period in writing. Our earlier guides on staged contractor payments and on comparing quotes with a BOQ explain how to set this up.

Bring these on the day:

  • The signed agreement, BOQ and any approved drawings.
  • A phone with a flashlight, a measuring tape and a small spirit level or a straight stick and a coin.
  • A bucket or jug, a phone charger or tester, a notebook, and masking tape to mark faults.
  • If you can, a civil engineer or experienced supervisor for half a day. The fee is small against the value of the building.

Go in daylight, then come back after dark, because lighting problems show up at night.

Outside and structure

Solar panels installed on a residential rooftop
Solar panels installed on a residential rooftop

Walk the exterior first. Look for diagonal or stair-step cracks near windows and corners, since those can signal movement, while thin hairline cracks in plaster are common and usually cosmetic. Check the boundary wall and gate for plumb, and test the gate lock.

On the roof, look for puddling and check slope towards the drains. Pour a bucket of water near the farthest corner and watch where it goes; if it pools for hours, waterproofing and slope need work before the next monsoon. See our guide on roof waterproofing and heat insulation for what the repair should look like and typical costs.

Also check the water tank, ideally by filling it and watching the walls over a day. Our guide on underground tank size covers what a 10 marla house usually needs.

Doors, windows and woodwork

Open and close every door and window. Doors should swing without scraping and stay where you leave them. Windows should lock, slide smoothly and close flush against the frame. If you chose uPVC or aluminium, check the glazing for scratches and the seals for gaps. Look at the gaps with the light off in a room; if you see daylight around the frame, dust, noise and smog will come through too.

Check wood for warping, uneven paint and loose hinges. Look inside cupboards for finished shelves, not rough ply, and check that drawers run properly.

Walls, ceilings and floors

Stand at the end of each room and sight along the wall with your phone flashlight held flat against it. Bumps and waves show up as shadows. Tap tiles with a coin: a hollow sound means the tile is not bonded well and will crack later. Run your hand across the joints for lippage, where one tile edge sits higher than its neighbour.

Check that floors slope towards the drain in bathrooms, kitchens and the porch, not away from it. Put a little water down and watch. In rooms, a marble or tile floor should not rock when you step on it.

For ceilings, look for stains, even faint ones, since they may indicate a past or current leak from the roof or an upstairs bathroom.

Plumbing

Open every tap, flush every toilet and run the shower for a few minutes. Look for:

  • Slow drains, which suggest blocked or badly graded pipes.
  • Low pressure at the farthest bathroom.
  • Leaks under basins and behind commodes.
  • Hot and cold water mixed up on a mixer.

Leave a bathroom floor wet for an hour and then check the ceiling or wall below. Ask your contractor to show you the manhole covers and confirm that sewer and rainwater lines are separate where your area requires it.

Electrical

Switch on every light, fan and socket. A cheap plug-in socket tester shows wrong wiring, missing earth and reversed polarity. Check that the distribution board is labelled, that breakers are the ratings that were agreed, and that heavy loads such as air conditioners and geysers have dedicated circuits. Turn on several appliances at once and see whether anything trips.

Confirm earthing exists. A house with no earthing risks shock and damaged electronics. Ask for the wiring layout photos taken before plaster, as we recommended in our guide on checks before plaster. If you plan solar later, see our guide on sizing a system for a 10 marla house and ask where the inverter and cable routes can go.

Kitchen and finishing

Test the kitchen counter for level, check that cabinets are fixed securely, and run the exhaust fan. Look at paint in raking light for patches, brush marks and roller lines. Check that the doors and drawers of any built-in wardrobes close fully. For a sense of what finishes should cost, see our kitchen renovation costs guide.

Document your findings and agree a fix list

Walk the house with a notebook and mark each fault with tape. Photograph every item with the room name visible. Then write a numbered snag list, with a column for the fault, the location and an agreed fix date. Both of you should sign it.

Sort the list into three groups:

  1. Safety and structure: wiring faults, active leaks, cracks that move. Fix before final payment.
  2. Function: windows, drainage, doors, locks. Fix within two weeks.
  3. Cosmetic: paint touch-ups, minor grout. Fix within the defect period.

If the contractor argues, point to the agreement and BOQ. Do not release retention until the safety and function items are closed.

Collect the paperwork

At handover, ask for any warranties on windows, waterproofing, water-proofing chemicals and appliances, as well as completion photos, and utility connection documents. Check that your gas, electricity and water meters are in your name, or in progress. If you are building in a society, confirm that a completion or occupancy process, if required by the society or authority, has been done; ask the society office what applies. Keep the snag list and photos for at least a year.

Your next step

Book the inspection for a weekday morning, not a Friday afternoon rush, and tell your contractor the date a week ahead so they can tidy up the obvious. Use the construction cost calculator to check your final bill against expectations, and keep the retention until the last item on your list has a tick next to it.

If you find more faults than you expected, stay calm and stay specific. A long snag list is normal in a new build, and most good contractors expect it. The contractors to worry about are those who dismiss every item, promise to "see to it later" without a date, or push for the final payment before you have finished looking. Keep the conversation about dates and items, not about blame, and keep every agreement in writing or on a message thread you can show later.

#Construction#Handover#Contractors#Inspection#New build

Frequently asked questions

What is snagging in a new house?

Snagging is a detailed handover inspection where you look for faults before accepting a finished building. You test taps, drains, wiring, windows, doors and floors, list every defect with photos, and agree fix dates with the contractor. It is best done before the final payment is released.

How much retention should I hold from a contractor?

Many owners agree to hold roughly 5% to 10% of the contract value for 30 to 90 days, but the amount and period are negotiable and should be written in your agreement. Release it only after safety and function items on the snag list are closed.

Who should inspect my new house at handover?

You can inspect yourself with a checklist, a tape, a bucket and a socket tester. For a larger build, paying a civil engineer or experienced supervisor for half a day is worthwhile, because they spot structural cracks, slope problems and wiring faults that are easy to miss.